0
  • DE
  • EN
  • FR
  • Internationale Datenbank und Galerie für Ingenieurbauwerke

Anzeige

Significant factors affecting the New Zealand transportation infrastructure project cost – quantity surveyors' perception

Autor(en): ORCID
ORCID

Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Built Environment Project and Asset Management, , n. 5, v. 13
Seite(n): 756-777
DOI: 10.1108/bepam-07-2022-0105
Abstrakt:

Purpose

Cost overrun is one of the critical issues faced in construction projects, as nine out of ten projects will likely go over the budget. In particular, transportation infrastructure (TI) projects, such as roads and bridges, are vastly affected by cost overruns, which can delay the entire project. This research intends to identify the factors affecting the cost overruns in New Zealand (NZ) TI projects.

Design/methodology/approach

The research was conducted using a questionnaire survey involving ninety-two participants experienced in infrastructure project estimation in NZ. Quantitative methods were used to analyse the data.

Findings

Fifty-three factors were identified through literature under ten categories. Based on the survey, ten significant factors were identified with a high grade of importance. The three most critical factors were “frequent design changes,” “poor planning and scheduling” and “inadequate tender documentation.” It was found that the cost overrun is primarily affected by the pre-contract stage causes.

Research limitations/implications

The data were collected from professionals involved in NZTI projects. Therefore, the implications may be different for other contexts.

Practical implications

The results will improve the current estimation practice by developing a new statistical model considering all the significant variables for NZTI projects.

Originality/value

Although much research is done to identify these factors, they are only considered in a few statistical cost models. These new statistical models mainly focused on technical variable factors similar to the current standard estimation process. However, the results of this research, qualitative and quantitative factors, will be used for the future cost model.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/bepam-07-2022-0105.
  • Über diese
    Datenseite
  • Reference-ID
    10738187
  • Veröffentlicht am:
    02.09.2023
  • Geändert am:
    02.09.2023
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine