Modeling schedule overrun and cost escalation percentages of highway projects using fuzzy approach

Autor(en):


Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 5, v. 24
Seite(n): 809-827
DOI: 10.1108/ecam-03-2016-0084
Abstrakt:

Purpose

Modeling represents the art of translating problems from an application area into tractable mathematical formulations whose theoretical and numerical analysis provides insight, answers and guidance useful for the originating application. The purpose of this paper is to determine the causal causes of schedule overrun and cost escalation of highway projects in Egypt in order to be used as independents variables in mathematical models for predicting the percentages of schedule overrun and cost escalation of such projects in Egypt.

Design/methodology/approach

A survey of a randomly selected samples yielded responses from 40 owners, 15 consultants and 56 contractors. The survey includes 38 schedule overrun factors and 26 cost escalation factors. The effectiveness degree of the identified factors has been identified by the triangle fuzzy approach.

Findings

The results of the survey show that “contractor’s technical staff is insufficient and ineligible to accomplish the project” is the most important cause of schedule overrun, while the major cause of cost escalation is inadequate preparation of the project concerning planning and execution.

Originality/value

The main contribution of this study is predicting the percentages of schedule overrun and cost escalation of highway projects in Egypt. Through the application of the linear regression analysis method and statistical fuzzy theory, four predictive models have been developed and it has been noted that the linear regression-based model shows prediction accuracy better than statistical fuzzy-based model in predicting percentages of schedule overrun and cost escalation.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-03-2016-0084.
  • Über diese
    Datenseite
  • Reference-ID
    10576583
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    26.02.2021
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine