Framework for enhanced progress tracking and control of linear projects

Autor(en):


Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 1, v. 21
Seite(n): 94-110
DOI: 10.1108/ecam-08-2012-0080
Abstrakt:

Purpose

This paper aims at improving progress tracking and control of repetitive projects by developing a novel framework that automates the documentation of as-built information directly into the project schedule and also introduces enhanced linear scheduling formulation to support project control decisions.

Design/methodology/approach

The proposed framework uses e-mail technology to facilitate detailed tracking of daily as-built events of all parties through bidirectional communication between site and head office. It also provides a new formulation for more accurate critical path and linear scheduling computation to accurately update the project's time and cost during construction.

Findings

Using a case study of a road project, the paper proves that the proposed framework reduces as-built documentation effort and its schedule updates are more responsive to all as-built events than traditional scheduling techniques.

Research limitations/implications

The proposed method applies to linear projects (e.g. highways) and can be extended to other repetitive projects such as high-rise buildings. It can also be extended to include voice features and procedures for forensic schedule analysis.

Practical implications

The developed methodology presents a low-cost approach to document timely progress information for decision makers of massive linear projects (often associated with infrastructure) to have better control over the execution of projects, save documentation time and cost, and avoid disputes and problems.

Originality/value

This research contributes in improving construction productivity by collecting timely as-built information using affordable communication technologies. It also presents novel advancements to the existing scheduling and control techniques to suit linear projects, which are most challenging.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-08-2012-0080.
  • Über diese
    Datenseite
  • Reference-ID
    10576414
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    26.02.2021
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine