Excavation of a tunnel with conventional method in urbanized context – A case study from Line 15 South of Grand Paris Express

Autor(en):



Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Geomechanics and Tunnelling, , n. 6, v. 16
Seite(n): 692-697
DOI: 10.1002/geot.202300031
Abstrakt:

As part of the Grand Paris Express project, the work package of Metro Line 15 South Lot T2C is situated near Villiers Sur Marne in the south‐eastern outskirts of Paris. It consists in two mechanized tunnels, principal as well as maintenance and storage site lines, respectively 4.7 and 2.2 km long, connected by a shaft approximately 180 m long (O807), 92 m of which is characterized by a traditional tunnel. This article presents the study carried out for the detailed design of the conventional tunnel which is excavated in the Calcaire de Champigny formation, a succession of layers with typical characteristics of a heavily fractured rock mass alternates with marly others, sometimes showing dissolution phenomena due to the presence of gypsum. Due to the urbanized context and the workface planning, a particular construction stage was also foreseen: the lower part of the section has been excavated by tunnel boring machine when the upper was finalized. The discussion is completed with the results of the monitoring activity, designed to check the correct behavior during and after the excavation process.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1002/geot.202300031.
  • Über diese
    Datenseite
  • Reference-ID
    10749378
  • Veröffentlicht am:
    14.01.2024
  • Geändert am:
    14.01.2024
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine