Cost optimization of project schedules under constrained resources and alternative production processes by mixed-integer nonlinear programming

Autor(en):

Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 10, v. 26
Seite(n): 2474-2508
DOI: 10.1108/ecam-01-2019-0013
Abstrakt:

Purpose

The purpose of this paper is cost optimization of project schedules under constrained resources and alternative production processes (APPs).

Design/methodology/approach

The model contains a cost objective function, generalized precedence relationship constraints, activity duration and start time constraints, lag/lead time constraints, execution mode (EM) constraints, project duration constraints, working time unit assignment constraints and resource constraints. The mixed-integer nonlinear programming (MINLP) superstructure of discrete solutions covers time–cost–resource options related to various EMs for project activities as well as variants for production process implementation.

Findings

The proposed model provides the exact optimal output data for project management, such as network diagrams, Gantt charts, histograms and S-curves. In contrast to classic scheduling approaches, here the optimal project structure is obtained as a model-endogenous decision. The project planner is thus enabled to achieve optimization of the production process simultaneously with resource-constrained scheduling of activities in discrete time units and at a minimum total cost.

Practical implications

A set of application examples are addressed on an actual construction project to display the advantages of proposed model.

Originality/value

The unique value this paper contributes to the body of knowledge reflects through the proposed MINLP model, which is capable of performing the exact cost optimization of production process (where presence and number of activities including their mutual relations are dealt as feasible alternatives, meaning not as fixed parameters) simultaneously with the associated resource-constrained project scheduling, whereby that is achieved within a uniform procedure.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-01-2019-0013.
  • Über diese
    Datenseite
  • Reference-ID
    10576860
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    26.02.2021
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine