Kingston Third Crossing

 Kingston Third Crossing
Autor(en): ,
Beitrag für IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019, veröffentlicht in , S. 921-927
DOI: 10.2749/newyork.2019.0921
Preis: € 25,00 inkl. MwSt. als PDF-Dokument  
ZUM EINKAUFSWAGEN HINZUFÜGEN
Vorschau herunterladen (PDF-Datei) 0.27 MB

Kingston Ontario is a city on the north eastern shore of Lake Ontario at the south end of the 202km long Rideau Canal, the oldest continually operated canal system in North America and a UNESCO Wor...
Weiterlesen

Bibliografische Angaben

Autor(en): (Brownlie Ernst & Marks (BEaM))
(Hatch)
Medium: Tagungsbeitrag
Sprache(n): Englisch
Tagung: IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019
Veröffentlicht in:
Seite(n): 921-927 Anzahl der Seiten (im PDF): 7
Seite(n): 921-927
Anzahl der Seiten (im PDF): 7
DOI: 10.2749/newyork.2019.0921
Abstrakt:

Kingston Ontario is a city on the north eastern shore of Lake Ontario at the south end of the 202km long Rideau Canal, the oldest continually operated canal system in North America and a UNESCO World Heritage Site. The Cataraqui river forms the lower portion of the canal and separates central Kingston from its eastern suburbs.

The Third Crossing is a new 1.2km long multi-span two-lane highway bridge across the Cataraqui river, planned to increase east-west journey capacity and reduce congestion on existing routes and crossings. The project is intended to facilitate a significant increase in bike journeys, minimize maintenance liabilities and maximize service life.

The project is believed to be the first bridge in North America to adopt an Integrated Project Delivery (IPD) model, involving an alliance of the city, design and construction partners. The city’s Preliminary Design was radically revised through the IPD process to bridge a significant affordability gap. Strict funding deadlines required the re-design to be completed within the short period allocated for validation of the original design. The IPD model allowed that undertaking to progress efficiently and keep the project on track in challenging circumstances.

The revised design addresses complex environmental, stakeholder and heritage issues. A key requirement to acknowledge the World Heritage asset is addressed with a weathering steel arched bridge spanning 100m across the river’s boating channel to form a dynamic gateway to the canal.