Construction on Antarctica: Dismantling an existing wharf structure
|
Bibliografische Angaben
Autor(en): |
Koen van Doremaele
(BAM (Delta Marine Consultants), Gouda, The Netherlands)
|
||||
---|---|---|---|---|---|
Medium: | Tagungsbeitrag | ||||
Sprache(n): | Englisch | ||||
Tagung: | IABSE Congress: Resilient technologies for sustainable infrastructure, Christchurch, New Zealand, 3-5 February 2021 | ||||
Veröffentlicht in: | IABSE Congress Christchurch 2020 | ||||
|
|||||
Seite(n): | 753-760 | ||||
Anzahl der Seiten (im PDF): | 8 | ||||
DOI: | 10.2749/christchurch.2021.0753 | ||||
Abstrakt: |
Rothera is the main mooring location in Antarctica for research vessels of the British Antarctic Survey (BAS). The existing wharf had reached the limit of its design life. To provide mooring of the new UK polar research ship, the RRSSir David Attenborough, a larger wharf structure was designed that required removal of the existing structure. This paper describes the engineering and technical challenges on providing a safe and stable structure during dismantling as well as the effects of icebergs, low temperatures and wildlife around this Antarctic research station. |
||||
Stichwörter: |
Kaimauer Demontage Antarktis
|