Procurement strategy and outcomes of a new universities project in South Africa

Autor(en):
Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 9, v. 26
Seite(n): 2060-2083
DOI: 10.1108/ecam-04-2018-0154
Abstrakt:

Purpose

Construction project management outcomes in the literature typically portray significant deviations from expected outcomes. Various theories from studies that focus superficially on causes of project cost and time overruns rather than root causes have not addressed this problem. The need is for a better understanding of how procurement strategy provides a fundamental means to address this problem. The purpose of this paper is to examine the procurement strategy used to deliver a new universities project in South Africa within budget and to ascertain its influence on the outcomes.

Design/methodology/approach

A case study was designed to provide a comprehensive and intensive methodology to identify and examine the construction procurement strategy and its influence on the project outcomes. Document analyses and semi-structured interviews were used to collect data on the construction procurement strategy and outcomes from the client team.

Findings

The evidence brought forward demonstrates that the successful outcome was largely a consequence of the client team, procurement strategy and systems of delivery. However, the collaborative procurement strategy formed the basis of the successful project delivery and outcomes. A general observation from the data is that an appropriate construction procurement strategy developed by an experienced client team and proactively implemented by an integrated delivery team working collaboratively is likely to achieve the intended project outcomes.

Practical implications

The findings show three critical keys to achieving intended outcomes – people, procurement strategy and systems of delivery at the governance, portfolio, programme and project management levels.

Originality/value

The value of this paper lies in using a comprehensive methodology to study the relationship between procurement strategy and outcomes. The findings can be applied by client teams to achieve better outcomes and value for money in infrastructure projects.

Geografische Orte

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-04-2018-0154.
  • Über diese
    Datenseite
  • Reference-ID
    10576826
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    26.02.2021
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine