Equity gap in construction contracting: identification and ramifications

Autor(en):

Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 1, v. 29
Seite(n): 262-286
DOI: 10.1108/ecam-09-2020-0725
Abstrakt:

Purpose

This study conceptualizes the equity gap (EG) in construction contracting and examines its impact on project performance.

Design/methodology/approach

The identification of EG was first summarized from a literature review. A conceptual framework that included EG elements of information, risks, expected return and power asymmetry was then proposed. A study of the Hong Kong–Zhuhai–Macau Bridge supported the existence of EG. The framework was further refined by incorporation of 21 EG identifications. To examine the reliability of the framework, data were collected from 106 senior project professionals to evaluate the extent to which EG identification occurred in their projects. A Partial Least Square–Structural Equation Modeling (PLS-SEM hereafter) analysis was conducted on the collected data.

Findings

The proposed framework was deemed statistically significant. Furthermore, no significant differences were detected between the developer and contractor. The concepts of asset and process specificities suggested that the unaddressed EG may be met with retaliatory behaviors, such as noncooperation, procrastination, opportunism and withdrawal, as the physical works proceed. These behaviors may also hamper project performance.

Practical implications

To address the EG ex post, it is suggested that relational incentives to balance the power differential be set, reallocation of risks and return and enhancing task programmability for ease of monitoring and performance evaluation.

Originality/value

This study investigates the downside of the EG between the contracting parties. The proposed EG framework informs the project management of critical EG elements and possible methods to narrow the gap ex post. Practical suggestions are also provided to manage construction contracts in general and in the use of incentive schemes to address EG.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-09-2020-0725.
  • Über diese
    Datenseite
  • Reference-ID
    10577121
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    24.02.2022
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine