General Information

Beginning of works: 2013
Completion: 18 September 2017
Status: in use

Project Type

Structure: Through arch bridge
Support conditions:
Function / usage: Road bridge
Material: Steel bridge
Plan view: Structurae Plus/Pro - Subscribe Now!

Location

Location: , ,
Address: 105 Street
Crosses:
  • North Saskatchewan River
Replaces: Walterdale Bridge (1913)
Coordinates: 53° 31' 42.28" N    113° 30' 5.91" W
Show coordinates on a map

Technical Information

Dimensions

main span 206 m
total length 230 m
arches height 56 m

Materials

arches steel
abutments reinforced concrete

Excerpt from Wikipedia

The Walterdale Bridge is a through arch bridge across the North Saskatchewan River in Edmonton, Alberta, Canada. It replaced the previous Walterdale Bridge in 2017. The new bridge has three lanes for northbound vehicular traffic and improved pedestrian and cyclist crossings.

Old Walterdale Bridge (1913–2017)

The previous Walterdale Bridge (formerly called the 105 Street Bridge, renamed in 1967) was a steel grating-decked truss bridge that spanned the North Saskatchewan River in Edmonton, Alberta, Canada. It was built in 1913 by the Dominion Bridge Company and was named after John Walter, an early settler who ran a ferry at this approximate location. The neighbourhood Walterdale at this location was also named after John Walter.

Demolition of the 1913 bridge began in October 2017 after the decking, sidewalks, and utilities had been removed, and was completed by the end of that year.

Replacement bridge (2017–Present)

Planning for the replacement of the 1913 Walterdale Bridge began over a decade before construction on the new bridge started. In 2001, an Edmonton City Council committee rejected a $190-million proposal for a tunnel under Saskatchewan Drive to directly connect the new bridge to Gateway Drive. Planners considered both a four-lane one-way bridge and a five-lane bridge with a single southbound lane to connect the area to Kinsmen park.

Construction began on a replacement bridge in early 2013 and was scheduled to be completed in late 2015; however, it did not open (two lanes only) until September 18, 2017. The contractor faced over $10 million in penalties for the delay. The new bridge has three lanes for northbound vehicular traffic and improved pedestrian and cyclist crossings. The old bridge was demolished and removed. Roadway and trail links north and south of the bridge were partially complete, and the pedestrian access and all lanes opened on September 29, 2017.

The new bridge is located east of the original bridge, and is supported by concrete thrust blocks on the banks of the river, eliminating the need for piers. The arches are 56 m (184 ft) tall.

Text imported from Wikipedia article "Walterdale Bridge" and modified on 27 September 2021 according to the CC-BY-SA 3.0 license.

Participants

Relevant Web Sites

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20081682
  • Published on:
    14/09/2021
  • Last updated on:
    06/01/2022
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine