General Information

Beginning of works: August 2014
Completion: 21 October 2016
Status: in use

Project Type

Location

Location: , ,
Coordinates: 53° 28' 52.07" N    113° 35' 54.03" W
Show coordinates on a map

Technical Information

Dimensions

total length 262 m
span lengths 77 m - 100 m - 85 m
number of cables 162
number of spans 3
deck slab thickness 0.465 m
piers number of piers 2

Cost

cost of construction Canadian dollar 24 500 000

Materials

deck prestressed concrete
piers reinforced concrete
abutments reinforced concrete