Rio Sul Center

General Information

Other name(s): UEB Center
Beginning of works: 1976
Completion: 1982
Status: in use

Project Type

Function / usage: Office building

Location

Location: , ,

Technical Information

Dimensions

height 168.00 m
number of floors (above ground) 51
office space 270 000 m²

Quantities

volume of extracted material 100 000 m³

Materials

pylons prestressed concrete
truss prestressed concrete
floor slabs prestressed concrete

Chronology

1972

Architectural studies.

1975

Basic architectural project.

1976

Beginning of construction.

1980

10-floor basement shopping center completed.

1982

Tower completed.