General Information

Beginning of works: 2003
Completion: 2008
Status: in use

Project Type

Structure: Southern bridge:
Suspension bridge
Northern bridge:
Cable-stayed bridge
Function / usage: Road bridge

Location

Location: , ,
Coordinates: 23° 4' 50.00" N    113° 28' 57.00" E
Coordinates: 23° 4' 17.00" N    113° 28' 34.00" E
Show coordinates on a map

Technical Information

Dimensions

width 41.69 m
total length 7 016 m
intermediate bridge
span lengths 6 × 62.5 m
northern approach viaduct
total length 1 775.5 m
span lengths 12 × 30 m - 12 × 45 m - 14 × 62.5 m
Northern bridge
main span 383 m
span lengths 383 m - 197 m - 2 × 62.5 m
pylon pylon height 226.14 m
pylon height (above deck) 160.45 m
southern approach viaduct
total length 3 080.5 m
span lengths 19 × 62.5 m - 18 × 45 m - 34 × 30 m
Southern bridge
main span 1 108 m
pylons pylon height 189 m

Chronology

14 February 2005

Construction of the northern channel bridge's deck begins.

28 March 2008

The deck is completed.

16 December 2008

The bridge is opened to traffic.

Advertisement

Participants

Currently there is no information available about persons or companies having participated in this project.

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20014846
  • Date created
    23/12/2004
  • Last Update
    05/02/2016