Grande Chaloupe Viaduct

General Information

Name in local language: Viaduc de la Grande Chaloupe
Beginning of works: 2014
Completion: 8 September 2017
Duration of works: 23 months
Status: in use

Project Type

Structure: Single-cell box girder bridge
Function / usage: Road bridge
Material: Prestressed concrete bridge
Construction method: Segmental construction

Location

Location: ,
, ,
Part of:
Coordinates: 20° 53' 43.76" S    55° 22' 34.30" E
Show coordinates on a map

Technical Information

Dimensions

total length 240 m
number of spans 4
girder depth 3.45 m
piers number 3

Quantities

concrete volume 15 000 m³
prestressing steel 350 t
reinforcing steel 2 300 t

Cost

cost of construction (incl. taxes) Euro 37 589 206.12

Materials

deck precast prestressed concrete
piers precast concrete
abutments reinforced concrete

Products, Services & Reports

mageba Pot Bearings are durable bearings that can be used in many situations, whether in big or small bridges, or a variety of engineering structur ...

[more]

On Réunion Island in the Western Indian Ocean, the strategically important ocean road RN1 linking the commercial port to the administrative capital ...

[more]