Saadiyat Bridge Abu Dhabi – One Bridge, Three Construction Methods

 Saadiyat Bridge Abu Dhabi – One Bridge, Three Construction Methods
Author(s): , , ,
Presented at IABSE Symposium: Sustainable Infrastructure - Environment Friendly, Safe and Resource Efficient, Bangkok, Thailand, 9-11 September 2009, published in , pp. 18-26
DOI: 10.2749/222137809796068064
Price: € 25.00 incl. VAT for PDF document  
ADD TO CART
Download preview file (PDF) 0.3 MB

The 1,450 meter long Saadiyat Bridge, the emerging landmark which will Link Abu Dhabi city with Saadiyat Island is one of the largest infrastructure projects in Abu Dhabi emirate. It will provide s...
Read more

Bibliographic Details

Author(s):



Medium: conference paper
Language(s): English
Conference: IABSE Symposium: Sustainable Infrastructure - Environment Friendly, Safe and Resource Efficient, Bangkok, Thailand, 9-11 September 2009
Published in:
Page(s): 18-26 Total no. of pages: 7
Page(s): 18-26
Total no. of pages: 7
Year: 2009
DOI: 10.2749/222137809796068064
Abstract:

The 1,450 meter long Saadiyat Bridge, the emerging landmark which will Link Abu Dhabi city with Saadiyat Island is one of the largest infrastructure projects in Abu Dhabi emirate. It will provide swift and smooth access to the signature destination which is being developed into a complete visitor and residential destination. Developed by

Tourism Development & Investment Company (TDIC), Saadiyat Island (Fig. 1) is the largest single mixed-use development in the Arabian Gulf. Saadiyat Bridge will carry 2 x 5 lanes of vehicular traffic and two tracks of light rail, plus special architectural features were incorporated such as a variable lighting concept which may be adapted to different occasions. Based on site conditions, the originally envisioned construction method was changed and a combination of incremental launching, span-by- span falsework and balanced cantilever construction was used. These three construction methods are presented in this article. Aside from the considerations that led to choosing these three methods, the advantages and disadvantages of each method are explained underlining specifically the economic aspects governing the choice.

Keywords:
incremental launching falsework Balanced cantilever construction segmental